Farm solar installation timeline from survey to grid export

Physical shed installation takes only 2 to 5 working days, even on a 30 to 50 kWp dairy or poultry roof. The real calendar driver is paperwork: allow 3 to 6 months for DAFM TAMS 3 written approval and 8 to 16 weeks for an ESB Networks NC7 Connection Offer.

Realistic Irish lead times for DAFM TAMS 3 tranches, ESB Networks Connection Offers, on-site shed work and grant drawdown.

Free, no obligation. One local installer prices it, not five.

  • 1–2 wkssurvey, MPRN review & quote
  • 3–6 mostypical TAMS 3 tranche approval
  • 8–16 wksESB NC7 Connection Offer study
  • 2–5 daysphysical farm shed roof install
Two solar engineers in hard hats reviewing system layout plans beside solar PV panels

Why planning two tranches ahead saves a full summer of bills

Spring-calving dairy farmers who wait until April to start pricing solar miss peak summer generation for that entire milking season because DAFM tranche scoring and ESB NC7 studies take months. Starting your survey in autumn or winter puts your agfood.ie approval and NC7 Connection Offer in hand by spring, letting the crew mount panels in 2 to 5 dry days right as daylight ramps up.

1. On-farm survey & quote

Typical duration
1 to 2 weeks
What happens on farm and on paper
Installer checks 12 months of MPRN bills, roof purlins, ESB supply and prepares the DAFM Solar PV Survey.

2. agfood.ie TAMS 3 tranche

Typical duration
3 to 6 months
What happens on farm and on paper
Advisor lodges application before tranche deadline; wait strictly for formal written DAFM approval letter.

3. ESB Networks NC6 or NC7

Typical duration
20 days (NC6) / 8–16 wks (NC7)
What happens on farm and on paper
NC6 clears in 20 working days; NC7 requires €1,041.81 fee payment and formal Connection Offer.

4. Shed installation & S.198

Typical duration
2 to 5 days on site
What happens on farm and on paper
Scaffolding/lifts, rail mounting, panels, inverter/battery wiring, commissioning and Safe Electric cert.

5. TAMS drawdown & CEG live

Typical duration
4 to 10 weeks post-claim
What happens on farm and on paper
Upload paid invoices, bank proof and S.198 certs on agfood.ie; claim VAT 58 / VAT 3; activate CEG export.

Price my farm solar

Four quick taps show your full ex-VAT cost and net cost after the 60% TAMS 3 grant before we ask for a phone number.

Dairy farm solar PV, 30 kWp array, with TAMS 3 60% grant: €11,200 to €15,600 net after 60% TAMS (full €28,000 to €39,000 ex-VAT).

Step 1 of 5

What type of farm is it?

Pick the closest. The installer reviews your annual bills on site.

How the farm solar figure is worked out

Guide ranges reflect typical Irish ex-VAT supply-and-fit agricultural PV rates (€1,000 to €1,400/kWp on sound steel shed roofs; €1,300 to €1,850/kWp ground-mounted) for panels, mounting rails, inverters, DC/AC cabling and DAFM S.198 commissioning. Net figures deduct the 60% TAMS 3 SCIS grant (paid on the lowest of actual ex-VAT invoice, proposed cost or DAFM reference cost up to €90,000). Optional battery storage (grant-aided up to 50% of solar kWp), ESB NC7 fee (€1,041.81 incl. VAT), purlin strengthening or asbestos roof replacement are priced after an on-farm survey. farmsolarpanels.ie is not DAFM, SEAI or a government body and does not award grants.

Keeping milking and yard traffic running during install week

Experienced agricultural installers schedule work around your yard routine rather than shutting the farm down:

  • Zero milking disruption: roof rail and panel crews work overhead while DC runs are pulled; the brief AC main-board shutdown for tie-in (usually 1 to 2 hours) is timed squarely between morning and evening milkings.
  • Clear yard access for lifts: keep one concrete apron bay free for scissor lifts or telehandler pallets of panels away from cattle lanes.
  • Commissioning handover pack: before final sign-off, collect your Safe Electric Completion Certificate, DAFM S.198 compliance pack, inverter monitoring app login, panel flash-test sheet and Triple E product codes.

Check TAMS 3 survey rules and what every quote should state before picking a tranche date.

Farm solar timeline questions

How long is the power turned off in the milking parlour during installation?

Only for the final AC distribution board connection and testing, typically 1 to 2 hours scheduled squarely between morning and evening milking.

Can I install farm solar without waiting 3 to 6 months if I skip TAMS 3?

Yes. Privately funded or SEAI NDMG projects do not wait on DAFM tranches, though NC6 still requires 20 working days notice and NC7 still requires a formal ESB Connection Offer before energising.

When should I book my on-farm solar survey relative to the next TAMS 3 tranche deadline?

Book your survey at least 3 to 4 weeks before the tranche closing date so your installer has time to measure roofs, check purlins, verify SSZ maps and hand clean documents to your agricultural advisor.

How soon after installation does DAFM pay the 60% TAMS 3 grant?

Once your paid invoices, bank proof, Safe Electric cert and S.198 paperwork are uploaded cleanly on agfood.ie and any site check clears, payment typically follows within several weeks to a couple of months.

All farm solar pages and guides

Two solar engineers in hard hats reviewing system layout plans beside solar PV panels